Monaghan County Council is delighted that construction commenced in July 2020 on this new and exciting project ‘Monaghan Peace Campus’. This €17.6 million project will provide a new four storey mixed use community building, comprising of a Cultural Heritage Centre, Library, Youth Facility, Shared Community Multi-Functional Space with External Community Space and Underground Parking.

This project is supported by the EU’s PEACE IV Programme, managed by the Special EU Programmes Body (SEUPB)  https://www.seupb.eu/

The financial support provided through the PEACE IV Programme is €9,541,081.

Monaghan County Council submitted an application in October 2021 seeking additional funding and SEUPB granted an additional €3.76million, therefore the revised total grant funding from SEUPB is €13,302,454.17.

Click here to read more: ‘Monaghan County Council Signs Contract For The Peace Campus Project

‘SEUPB Project Case Study – Progress to Date’ – Please find a link HERE

 

Drone Footage of the Peace Campus Progress - March 2024

Progress to Date - Monaghan Peace Campus Time Lapse Footage September 2020 to February 2024

Summary of Progress to Date:  Q4 2023 (Oct – Dec 2023)

  • Painting, decorating and tiling nearing completion;
  • Electrical containment (2nd fix) substantially complete;
  • Mechanical Installation (2nd fix) substantially complete;
  • Joinery (2nd Fix) substantially complete;
  • Soft Landscaping substantially complete;
  • Eir & ENET (Utilities) substantially complete;
  • External Railings – Installation substantially complete;
  • Paving of external areas almost complete.

Summary of Works Completed:

  • Level 4 flat roof coverings, insulation and plant guarding complete;
  • Electrical containment (1st fix) on all Levels complete;
  • Mechanical installation (1st fix) on all Levels complete;
  • ESB connection to substation complete;
  • Installation of built in furniture complete;
  • Lift installation completed – final snagging and commissioning commenced;
  • Gas Tank and Gas Boilers installation works complete.


Summary of Progress to Date:  Q3 2023 (July – Sept 2023)

Works Ongoing:

  • Level 4 flat roof coverings and insulation nearing completion;
  • Painting, decorating and tiling ongoing;
  • Electrical containment (1st fix) on all Levels substantially complete;
  • Electrical containment (2nd fix) ongoing;
  • Mechanical installation (1st fix) nearing completion on all Levels (0 – 4);
  • Mechanical Installation (2nd fix) ongoing;
  • Joinery (2nd Fix) ongoing;
  • ESB works for power supply ongoing;
  • Soft Landscaping works ongoing;
  • Gas Tank installation works ongoing;
  • Eir & ENET (Utilities) works ongoing.
 

Works Completed:

  • Installation of zinc cladding to Level 4 roof completed;
  • Joinery (1st fix) & Timber screens completed;
  • Bench Seating brackets to Planters completed;
  • Level 4 Multi Use Room – Roof works completed
  • External & Internal brickwork complete.
 

Summary of Progress to Date:  Q2 2023 (Apr – June 2023)

Works Ongoing:

  • Roof works to Level 4 Multi Use Room nearing completion;
  • External & Internal Brickwork substantially complete;
  • Curtain walling framing and glass installation;
  • Painting and decorating;
  • Electrical Containment (1st fix) on Levels 1, 2, 3 & 4;
  • Mechanical Installation (1st fix) on Levels 1, 2, 3 & 4;
  • Joinery (1st fix) and timber screens;
  • ESB works for power supply. 
 
 

Works Completed:

  • Stone Cladding on building;
  • Level 3 Community Room Roof Works;
  • Installation of floor insulation and screed on Levels 2, 3 & 4;
  • Level 4 Glass Balustrade bracket works
  • Roof finish to External Stage

Summary of Progress to Date:  Q1 2023 (Jan – March 2023)

Works Ongoing:

  • Roof works to Level 3 Community Room and Level 4 Multi Use Room
  • External & Internal Brickwork
  • Curtain walling framing and glass installation
  • Electrical Containment (1st fix) on Levels 1, 2 & 3
  • Mechanical Installation (1st fix) on Levels 1, 2 & 3
  • Installation of Stone Cladding to External & Internal areas
  • Installation  of Zinc Cladding to Level 4 roof
  • RC Snagging to external elements
 

Works Completed to date:

  • Insulation and wall tie channel restraint system installation to external facades
  • External SFS Stud & Framework installation to all levels
  • Level 4 Glass Balustrade bracket works
  • Roof finish to External Stage
  • Installation of Level 2 floor insulation and screed
  • Podium Deck area outside Staircore 1 and North Road concrete installed
  • External Stair 2 from Level 0 to Podium Deck
 

Summary of Progress to Date:  Q4 2022 (Oct – Dec 2022)

Works Ongoing:

  • Electrical Containments on Levels 0 – 1
  • Installation of Windows (Glass)
  • External & Internal Brickwork
  • Roof Works to Level 4 Multi Use Room
  • Roof Works to Level 3 Community Room
  • External SFS Stud and Framework installation to Levels 1 – 4.
  • External Stair 2 from Level 0 Podium deck
  •  

Works Completed to date:

  • External Stair flight 3 and landing including walls complete;
  • Podium Deck area at Staircore 1 and North Road prepared and concrete installation complete;
  • 24 no. Window Frames installed around all facades of building;
  • Formation of concrete external Stair beside ESB Substation complete;
  • Lower Planter Walls complete;
  • Walls to External Stage area complete.

Progress to Date:  Q3 2022 (July – Sept 2022)

Works Ongoing:

  • Internal Installation of SFS commenced on Level 1
  • Installation of IG Masonry supports ongoing at Level 2
  • Works to Planter Walls ongoing.
  • Works on External Stage Area have commenced.
  • Brickwork ongoing at Levels 1 – 4 on all elevations

 

Works Completed to date:

  • Insitu concrete stairs formed up to Level 4 slab in Staircore 1.
  • Internal Stair 2 flights and landings from Levels 1 – 3 complete.
  • Works on Level 4 parapet walls and Lift shaft complete.
  • Brickwork at Level 0 complete.
  • ESB Substation: Brickwork and PVC Roofing complete.

Progress to date: Q2 2022 (April – June 2022)

Works Ongoing:

  • Electrical Containment installation at Level 0 almost complete;
  • Level 4 formwork ongoing;
  • Brickwork commenced at Level 0 – Internal & External;
  • Installation of SFS walling;
  • Installation of IG Masonry supports.
 

 Works Completed to date:

    • Level 3 – 4 Columns;
    • Staircore 1 Level 3 walls;
    • Level 4 slab poured;
    • Construction of ESB Substation brickwork;
    • Concrete Stairs formed up to Level 3 in Staircore 3;
    • Concrete Stairs formed up to Level 2 in Staircore 1.

Q1 2022 (January to March 2022)

Works ongoing:

  • Casting of North Road retaining wall
  • Construction of Stairs 1 & 3 at Level 2
  • Formwork on Level 3 commenced
  • Formwork to Atrium Wall ongoing

Works completed to Date:

  • Casting of Level 0 slab
  • Casting of Level 1 and Podium Slab
  • Casting of Level 1 – Level 2 columns
  • Casting of Level 2 slab
  • Casting of Level 2 – Level 3 Columns

Progress to Date

Q4 2021 (October to December 2021)

Works ongoing:

  • Casting Level 0 – Level 1 Columns
  • Installation of temporary Soffit formwork to Level 1 area
  • Tying of reinforcement and casting concrete slab to Level 1 area
  • Tying reinforcement on Level 1 – Level 2 Structural Columns
  • Casting reinforced concrete walls to Level 1 Stair 3 core
  • Erection of temporary framing to section 2 North Road retaining wall
  • Casting of substation trench walls and pits.

Works completed to Date:

  • Substructure piles, pile caps and associated foundation
  • Storm drainage and foul pipework beneath Level 0
  • Majority of Level 0 reinforced concrete slab now cast
  • Reinforcement and concrete works to Level 0 – Level 1 structural columns
  • Level 0 lift shaft and structural walls
  • Section 1 of North Road retaining  wall
  • Perimeter drainage works and filter drains

Progress to Date

Q3 2021 (July to Sept 2021)

Works ongoing:

  • Casting of Level 0 carpark concrete slab ongoing
  • Tying reinforcement steel to Level 0 – Level 1 structural columns ongoing
  • Tying reinforcement steel to Level 0 carpark slab substantially complete


Works completed to Date:

  • Project Signage Boards at 3 nr. Locations erected
  • Piling works and associated pile cap foundations
  • Construction of Podium ramp structure
  • Sub-floor drainage, interceptors and ducting works
  • Construction of retaining walls ongoing including temporary works framing
  • Sub-floor drainage, interceptors and ducting works
  • Attenuation tanks and culvert replacement works

Progress to Date

Q1/Q2 January-June 2021

Monaghan Peace Campus Construction site was closed from 8th January 2021 due to Covid19 Public Health Measures & Restrictions. Site re-opened 4th May 2021.

Works completed to date include:

  • Temporary Safety Barriers installed along North Road
  • Culvert and associated chamber installed
  • Level 1 podium ramp structure complete
  • Attenuation tanks cast and precast cover slabs placed
  • Electrical switch room cable trench cast
  • Foundations cast and sub-structure masonry walls built to base of new stone walls at Glaslough St.

 

Works currently ongoing include:

  • Sub-structure works to include pile caps and associated structure foundations
  • Preparation of sub-station floor in progress to receive cable trenches
  • Lift shaft on Level 0 cast and waiting Level 1 deck slab
  • Casting of Pile caps 98% completed
  • Temporary shorting erected to Stage 1 of North Road Retaining Wall
  • Tanking membrane applied to approx. 50% of North Road retaining wall
  • Installation of Storm drainage network ongoing at Level 0

Monaghan Peace Campus Q1/Q2 January-June 2021 – Click on the images below for a larger image.

Progress to Date

Q4 September-December 2020 

Works completed to date include:

  • Establishment of site compound, office and welfare accommodations.
  • Installation of foundation bearing piles and associated mini pilling.
  • Erection of Tower Crane and associated foundations.


Works currently ongoing include:

  • Casting of foundation pile caps, ground beams and associated stair core foundation slabs.
  • Fixing of reinforcement to pile caps, level 0 structural columns, level 0 podium ramp walls and level 0 stair core walls.
  • Construction of ESB sub-station.
  • Construction of level 0 lift core structure.
  • Construction of 2 nr. Attenuation tank bases.
  • Storm drainage pipework and service ducting.

Monaghan Peace Campus Q4 – Click on the images below for a larger image.

Q3 July – September 2020 The site is secure and hoarding is erected.  Existing perimeter structures have been demolished. Clearing of site is completed.  A Time Lapse camera has been installed.  Test Piles installed and tested.  Piling is complete.  Contractor has liaised with neighbouring residents and Government Departments.